工序流程文件範本 - 電腦房精確冷氣清洗新喉管 Method Statement for Pipes Installation (CRAC)

Method Statement for CRAC Installation



1. Introduction
        ABC Engineering Limited, former of ABC Engineering Limited established the business in Hong Kong since 2018. In the year of which ABC was established, we had expanded our scope to Telecommunications industry. To date, we have well over 14 years of experience in the Telecommunications industries. The experience and expertise acquired by our resource teams have enabled the company to offer to our clients turn-key solutions across a full range of projects and technologies, including mobile communications (GSM / PCS / CDMA / GPRS / 3G etc.) and wireless access (LMDS / 2.4 & 3.5G BWA etc.).
        In addition, our technology experts and skilled labours are complemented by highly efficient
and effective project management and support teams assisting our clients to achieve the
fastest Return-On-Investment (ROI) possible.
This method statement of CRAC installation to Client by ABC Engineering Limited for the upgrade of CRAC system at Site Address.
1.1 Scope of a method statement
        The scope of method statement designed to prove installation pipework quality on 1 January
2018. The newly installed water pipe (around 2 meters) is extended from existing chilled water
pipe to our proposed CRAC. The method statement is to test any water leakage from the new installed 2 meters water pipe and CRAC.
1.1.1 Methodology of the pressure test
The pressure test is required for the following test equipment.
• Pressure Guage (Brand: Y.F and identification no: PG-01) – Product brochure and calibration certificate are attached.
• Pressure Pump
        Using the above equipment, checking all the pipes are connected correctly and properly. The
pressure test is proposed to take four hours duration. During the test, the pressure is increased to 120 lb (equivalent to 54.5kg) inside of the pipe. BeSpark will monitor the reading of pressure inside the pipe. If the reading of pressure lies between ± 5%, it means the pressure test is satisfied the pressure requirement.



        After confirmation of the test result is passed the pressure test requirement, ABC will add salver at the testing area to prevent the water stained on the floor. After complete of CRAC installation, ABC will clean up the site and make up the thermal insulation on the pipe. The above pressure test will be held on 16 August morning period.

 The other test for water pipe flushing will be held on 16 August afternoon period, the detail of the test procedure is listed as below.
• Disconnect the CRAC unit piping
- Fill-in water to new piping, and use a small pump to circulate the water
• Drain out all water and re-fill fresh water. Circulate the water around 2-4 hours
• Fill-in the chemical and run around for 2 days, after filling the chemical, drain and refill the
water

• Take water sample for analyzes
• Submit the water sample report to Client
1.1.2 Power connection to CRAC
The power connection to CRAC will be connected from 2 x 63A power sources, and the connecting cable is used 2 pieces of 16 mm sq. XLPE/SWA/PVC Cu. Cable and CPC. The power source will be teed off from 8th floor Main L.V. switch room (W) to the proposed CRAC location. Another 32A power is required toted off from 8th floor Main L.V. switch room (N) to the proposed CRAC location. It is required to use 1 piece of 6 mm sq. XLPE/SWA/PVC Cu. Cable and CPC. Other than the above material, it will be installed of 2 x 63A TPN isolator and 1 x 32A TPN isolator with trunking.

<- END ->


CRAC - Computer Room Air Conditioner 




本人的其他Blog

申請你的紐西蘭電業牌照及駕駛執照
Application your EWRB and Driving License in NZ
applicationnz.blogspot.com

紐西蘭生活 New Zealand Live
newzealand1943.blogspot.com

香港遊蹤  Signseeing Hong Kong
sightseeinghongkong.blogspot.com

沒有留言:

發佈留言

任何人留有政治言論,個別使用者將會被隔離這個網誌,或留言系統將會被限制,甚至關閉。
所有技術性問題,必須在網誌內進行提問,讓其他人也可以觀看,其他社交軟體一律不作回應,所以不用償試在其他社交軟體尋求一對一的提問。
如果進行匿名留言,有時候系統會當作垃圾訊息,需要審批才會出現,時間上會較遲。